Seismic Retrofit – Kaiteriteri Home

Location
Kaiteriteri

Drilling Project Details
This project involved the drilling and installation of 36 anchors to stabilise an existing retaining wall and basement of a residential home after Cyclone Gita.

The anchors were drilled and installed 9m into Separation Point Granite, walers installed over the anchors to complete.

Challenges included working inside the building, and drilling/casing through loose drainage material behind the basement, this was overcome by vacuum advancing UPVC casing through the concrete wall and seating into the granite behind. This ensured that the drainage materiel is left insitu and remains fully functional.

Drilling Equipment Used

Tadano Multi-Drill.

Hydro 200 Drill Rig.

Result

Project successfully completed within budget and the expected timeframe.