Geotechnical – Picton Foreshore
Location
Picton Foreshore, Marlborough
Drilling Project Brief
Carry out investigative geotechnical drilling for proposed foreshore development (development is now completed).
Drilling Project Challenges
Working close to a sensitive marine environment
Existing businesses still operating in a busy tourist area
Tidal movements
Multiple holes required, including several from barge
Result
Successful geotechnical core samples delivered on time and within budget.
Enquiry
Related products
-
Geotech Drilling – Tunnel 21 Seddon
Read moreGeotechnical project carried out for T&T and KiwiRail. Due to Kaikoura earthquake this tunnel was damaged and the hill was to be cut down to ‘Daylight the Tunnel’, out work was to identify strata.
-
Retaining Wall – Motueka Valley
Read moreExtensive damage due to Cyclone Gita. Project included earthworks and excavation, large diameter holes for cemented retaining wall posts, drilling and installation of ground anchors to support completed wall.
-
Geotechnical Drilling – Karamea Road
Read moreDrilled 20 boreholes using two different methods, HQ TT Core in cohesive materials, and concentric casing advancement in loose colluvium. All holes were drilled in or above landslide debris.
-
Geotechnical Drilling – Deans Head
Read moreTwo Geotechnical holes required, PQ Cored to 35-40m depth through landslide to assist Geotechnical Engineers. Location required helicopter access so we used our fly rig (QM750).