Drilling Project Brief
Project involved drilling a single core hole in PQ TT to 25 metres carrying out SPT testing at 75m intervals.
The major challenge to this interesting project was gaining access over busy ski lanes and soft snow covered ground conditions, we required assistance with a snow groomer to tow our Hanjin 8D rig to site. This rig was selected due to its light weight, and low ground pressure required to gain access over in some places very soft deep snow.
We were also assisted greatly with Cardrona staff making access to / from the site on a daily basis easy with a quick ride on a skidoo.
Drilling Project Challenges
Soft and deep snow ground conditions.
Gaining access through busy ski lanes.
Very cold working environment.
Result
The drilling was completed on time, and within budget, with good recovery in tricky ground. Other than being very cold, the weather for the duration of the job was perfect.
Enquiry
Related products
-
Road Repairs – Takaka Hill
Read morePost cyclone Gita the Takaka Hill road suffered extensive damage. Emergency Works included Geotechnical drilling, large holes for retaining walls, and many ground anchor installations.
-
Seismic Retrofit – Kaiteriteri Home
Read moreThis project involved the drilling and installation of 36 ground anchors to stabilise an existing retaining wall and basement of a home in Kaiteriteri, Tasman after Cyclone Gita.
-
Horizontal Drilling – Takaka Hill
Read moreRequired to drill and install temporary casing through a variety of formations to allow the installation of 80mm conduit to carry broad band cables for Golden Bay.
-
Exploration Drilling – West Coast
Read moreImmediate drilling required in remote and extremely steep country all within typical dense West Coast bush.